skip navigation
New York State Home Page
SUCF Logo
State University Construction Fund
Home
About SUCF
Mission Statement
Organization Functions
Contact SUCF
Integrity Hotline
SUCF Employment
FOIL
Archived Webcasts
Site Map
Business/Contracting Opportunities
Procurement Contacts
Construction Bid Activity
Construction Bid Calendar
Construction Bid Results
Consultant Selection Guide
Consultant Selection Status
Design and Construction Resources
SUCF Campus Assignment
Forms
Bulletins, Directives and Agreements
NYS Contract Reporter
MWBE Automated Directory
NYS Tax and Finance Forms
Prevailing Wage Rates
Community College Forms
Projects
SUNY Capital Master Plan
Current Activity
Construction Locations
Design Locations
Environmental Impact Statement
Web Cameras
Photo Gallery
SUNY Facilities
Campus Maps
Rockefeller Institute Report on SUNY Facilities
Facilities Home Pages
SUNY Physical Plant
Facility Inventory Manual
SUCF Applications

SUNY Empire State College

Construct Distance Learning Center

These are static photos of the project. You can also view a screen show that enables you to step through the static photos or you may have the screen show play for you.

Screen Show

Photo: Exterior Elevations from Southeast, 05/30/07 Photo: Exterior elevations from Northwest, 05/30/07 Photo: Drilling Geothermal Wells, 03/18/08 Photo: Excavation for Building Foundation, 03/18/08
Exterior elevations
from Southeast
05/30/07
Exterior elevations
from Northwest
05/30/07
Drilling
Geothermal Wells
03/18/08
Excavation for
Building Foundation
03/18/08
Photo: Existing Paving & Site Lighting Demolished, 03/18/08 Photo: Extension of Water Line, 03/18/08 Photo: Foundations South Wing, 05/23/08 Photo: Backfilling Foundations & Plumbing East Wing, 05/23/08
Existing Paving
and Site Lighting
Demolished
03/18/08
Extension of
Water Line
03/18/08
Foundations
South Wing
05/23/08
Backfilling Foundations
Plumbing
East Wing
05/23/08
Photo: Steel Erection South Wing, 05/23/08 Photo: Steel Erection South Wing, 05/23/08 Photo: Steel Erection South Wing, 06/24/08 Photo: Steel Erection North Wing, 06/24/08
Steel Erection
South Wing
05/23/08
Steel Erection
South Wing
05/23/08
Steel Erection
South Wing
06/24/08
Steel Erection
North Wing
06/24/08
Photo: Main Building Entrance Steel Erection Complete, 07/07/08 Photo: South Wing Underslab Utilities Complete, 07/07/08 Photo: Concrete Finishing, 07/29/08 Photo: North Roof Angle, 08/04/08
Main Building Entrance
Steel Erection Complete
07/07/08
South Wing Underslab
Utilities Complete
07/07/08
Concrete Finishing
07/29/08
North Roof Angle
08/04/08