| Project | Description | Architect | General Contractor | Status |
|---|---|---|---|---|
| 12260 | REPLACE WINDOWS/REPOINT BRICK - CRUMB LIBRARY | ARCHITECTEAM SCHLEICHER-SOPER | CONTINENTAL CONSTRUCTION, LLC | Under Construction |
| 12268 | Exterior Safety Enhancements - Campuswide - Site | CLOUGH, HARBOUR & ASSOCIATES, LLP | ACTS II CONSTRUCTION,INC. | Under Construction |
| 12286 | Rehabilitate HVAC - Crumb Library | SAGE ENGINEERING ASSOCIATES, L.L.P. | NORTHERN MECHANICALS,INC | Under Construction |
| 12315 | REHAB POOL AREAS AND EQUIPMENT-MERRITT AND MAXCY HALLS | SAGE ENGINEERING ASSOCIATES, L.L.P. | CONTINENTAL CONSTRUCTION, LLC | Under Construction |
| 12322 | UPGRADE LOCKER ROOMS, MAXCY HALL | SAGE ENGINEERING ASSOCIATES, L.L.P. | CONTINENTAL CONSTRUCTION, LLC | Under Construction |
| 12332 | Upgrade Underground Site Infrastructure - Site Improvements, Phase I | GREENMAN-PEDERSEN, INC | BARRETT PAVING MATERIALS, INC. | Under Construction |
| Potsdam Total | Total Construction Award Value | $6,534,900 |